Bridge Demolition On The UK’s Busiest Motorway!

TRU Demolition complete high pressure bridge removal and clearance on the UK’s busiest motorway.

In partnership with Balfour Beatty, Clarke Demolition Company (part of the Tru7 Group) undertook the demolition of Clearmount Bridge for National Highways between Junctions 10 and 11 of the M25, on Friday 15th through to the early hours of Sunday 17th March. This was the first-ever planned closure of the M25 since its completion in October 1986 and garnered significant public interest, due to the perceived negative impact on the strategic road network.

The traffic management and media comms were extremely effective and reduced the traffic flow on the M25 significantly, allowing CDC to commence the demolition as planned on Friday evening.

Works consisted of the demolition of the RC bridge deck, the cutting and lifting of supporting beams to ground level for processing, and the demolition of both abutments. All concrete arisings are being processed into granular material in accordance with the circular economy principles for construction. In addition to processing arisings into construction materials, all arising steelwork has been sent for recycling; ensuring the scheme maintains its recycling and environmental objectives.

Another safe, well-planned, and well-executed project, resulted in the motorway being opened a full 8 hours ahead of the scheduled time.

Dive into our behind-the-scenes YouTube video for some raw footage of the action on the first shift below:

 

Related Articles

Meet our team

Meet the team behind TRU7 Group and get in touch with us to find out more information on how we can help you.

Meet the team

JOIN US

TRU7 Group are rapidly expanding, and as such, we are constantly on the lookout for professionals to join our ever-growing team.

Find out more

TRU7 Ltd – Reg No: 00341968 | Nicholls Ltd – Reg No: 09556852

Website by Unity Online